Project Zeus includes ten Tier III data centers on a greenfield site. The first two buildings each include four 7 MW data halls and one 8 MW network for a total of 36 MW per building. Each of the third through tenth building includes three data halls that total 36 MW. The project also includes 195 acres of site preparation and underground utilities for the final five buildings.
- Total building: 250,000 sq ft total each
- White space: 36 MW per building
- Tier level: III
- Total critical IT load: 360 MW
- Type: Greenfield hyperscale